Question: Should I ever pay the builder upfront, say to get some specific materials?

Answer: It’s not common practice, so make sure to sign a contract that’s fair to both parties before work starts.

This is a question that often causes debate. Contractors who seek this upfront payment are often builders who have previously had an issue receiving payment from their clients. It is understandable that they would therefore seek to manage that risk differently.

I, however, never advise any form of payment upfront as a rule. You should only be paying general building contractors or tradespersons for work they have completed. This is one of the many reasons to have a contract in place with your builder at the start, to avoid any disputes or misunderstandings.

Every business needs cash flow to buy materials, carry out the work, claim payment and get paid, so there is always a lag in the period between them incurring costs and when they receive payment. Companies whose main cost is their own time and general building materials will have these lags built into their business model.

The majority of reputable contractors have trade credit and will often not pay for any materials for at least a month.

Most of the companies that seek payment in advance are companies supplying materials that they themselves must order. Those that simply will not place an order without a deposit include those supplying windows, kitchens, tiles and sanitaryware. If the builder requests payment for these specific elements, suggest you pay for these yourself. It’s a good idea to deal with these companies directly anyway, in case anything goes wrong.

If you’re getting the house built turnkey from a kit supplier, a schedule of payments for everything will be set out from the get-go.

Some contractors may claim that a payment upfront is a gesture of goodwill. In a market where this is simply not standard practice, there is no reason to go down this route and it places the risk entirely at your door that the work is done to the highest standards, that it will be completed in full and that the contractor has a reason to finish the work.

Obviously, the contractor is taking a risk in their client actually paying them for the work they complete, but that is the industry they work in and in the majority of cases they get paid without any issues. There is after all a very small percentage of disputes in the industry relative to the volume of work carried out each year.

It’s worth pointing out that most contracts will include a provision to hold back a small amount at the end, to ensure the snag list (small things to fix) gets done. It’s referred to as ‘retention’ whereby a percentage of all payments to the contractor (usually 5 per cent) is retained until substantial completion. It ensures a carrot and stick approach to ensuring that the contractor will complete the project and remedy any snags or defects at the end.

Half of the value of the retention is released to the contractor at practical completion and the remaining 50 per cent is held for the defects liability period. How long this lasts is agreed to in the contract, usually from three months for minor projects to 12 months for a new build property. At the end of the defects liability period, once all snags/defects are remedied, the balance of retention is released to the contractor.