In this article we cover:

  • How to make sure your application is valid under the new rules
  • Changes to further information requests
  • Making minor changes to an existing planning permission
  • New deadlines for planning decisions and appeals
  • Changes to planning objections
  • Changes to how long planning permission is valid
  • What happens if you’ve already submitted your planning application

How you can apply for planning permission in Ireland is changing, with the last changes to the Planning and Development Act coming into force on November 26th, 2026.

Minister for housing James Browne and minister of state for local government and planning John Cummins have confirmed that the remaining provisions of the Planning and Development Act 2024 will come into operation on November 12th, 2026, three years after the publication of the planning bill.

The government says the changes will help reduce delays, cut red tape and speed up housing delivery.

Invalid applications

Applications validated by midnight on Wednesday, November 25, will continue to be assessed under the Planning and Development Act 2000, while new applications entering the system from Thursday, November 26, will fall under the 2024 Act.

If you’re still putting your planning application together, make sure you’re using the new application forms, site notices and newspaper notice templates.

Local authorities have warned that using documentation that refers to the old planning legislation could result in your application being declared invalid. The updated forms are available through local authority websites.

According to architectural workshop David Williams & Co, applications will need more work up front including documentary proof that the applicant is entitled to apply: proof of ownership, or the owner’s written consent. Newspaper and site notices must be given within the two weeks before lodgement, and a council can invalidate an application even after acknowledging it if the notices were deficient.

Further information requests

David Williams & Co says the biggest change is to further information, which is when an application requires more documentation to be assessed. The onus will be on having any necessary surveys and reports done at the design stage.

Under the new rules, a local authority will be able to ask only once, within eight weeks, for further information. “On a standard application, the request will be limited to matters that couldn’t have been foreseen, new issues raised in submissions, or checking what was already provided,” reads the David Williams & Co analysis.

“An application lodged with gaps, on the expectation that a request will fill them, is now more likely to be refused. For our clients, this moves cost and time to before lodgement. Surveys, drainage, daylight studies and heritage assessments should be done at design stage. They cost the same whenever they’re done, but after lodgement they may come too late to avoid a refusal.”

Easier to make changes

Getting planning permission to build your own home can be a long, costly and sometimes frustrating process. From waiting months for a decision to having to reapply for permission when your plans change, there are plenty of hurdles along the way.

So one of the more welcome changes is likely to be the introduction of a simpler process for making minor alterations to an existing planning permission.

It’s not unusual for house designs to evolve between getting planning permission and starting work on site. Under the new system, it may be possible to make minor changes without the cost and hassle of going through the planning application process all over again. Exactly what types of design changes will qualify remains to be clarified.

Changes to appeals

Anyone who has had a planning application go to appeal will know how frustrating the wait for a decision can be. Under the new rules, statutory deadlines will apply across the planning process, including to decisions made by An Coimisiún Pleanála (formerly An Bord Pleanála).

Knowing when a decision is due should make it easier to plan ahead, particularly when it comes to securing finance, booking tradespeople and agreeing a start date you’re your builder.

While people will still have the right to raise genuine concerns about a proposed development, new measures are being introduced to prevent misuse of the planning system.

Anyone submitting an observation or objection will now have to declare that they are not doing so simply to hold up a development or in an attempt to secure payment.

Also, the clock on a planning permission will effectively stop if it is challenged through the courts. This means that the time spent dealing with a judicial review will no longer eat into the period homeowners have to complete their build.

Other changes

Local authorities will now have eight weeks to decide on most applications, although they can request an extra four weeks. As before, planning permission lasts five years by default, but you can apply for it to be valid between two to 10 years and it can be extended only once.

Also, the Section 5 declaration becomes a Section 10 declaration, and the Section 57 declaration for protected structures becomes a Section 310 declaration. Owners in Architectural Conservation Areas get a new right to ask which works need permission.

Changes to the County Development Plans are also going ahead as planned. Each local authority will now publish a 10-year CDP with a review at the halfway point.

While these changes are designed to make the planning process more straightforward, for many would-be self-builders the bigger question is whether it will become any easier to get permission to build a home in the countryside.

The much-anticipated overhaul of Ireland’s rural housing policy is, however, separate from the legislative changes to the planning system.